Sewer & Water Utility
Description of Project:
Replace sewer main.
Location:
Lake Rd/County Hwy CV
Timeline:
2025.
Update as of 5/2/2025 -
Work Completed This Week:
- Contractor completed sanitary sewer on CTH CV from Windsor Road to 1st Street
Work Anticipated Next Week:
- Prep road base and pave roadway above the sanitary sewer on CTH CV from Windsor Road to 1st Street