Roadwork Projects
Village street projects are determined based on street review and condition rating.
Work anticipated the week of 11/9/25: Road Closure Map
Work Completed This Week:
- The utility crew completed a utility adjustment at Windsor Commons Avenue.
- The road crew continued preparing the roadway for paving.
Work Anticipated Next Week:
- The contractor will continue to prepare the remaining roadway for asphalt. Affected traffic access routes will be updated on the changeable message boards.
- The paving crew is scheduled towards the middle of the week to complete the remaining asphalt, weather permitting.
Dane County Schedule
- This Week: The County utility crew #1 completed reconstructing the culvert crossing just north of Innovation Drive.
- Next Week: County utility crew #1 will start the culvert crossing between 4th Street and Diamond Drive.
- The County work will involve road closures throughout the week.
- Additional information and their construction map can be found by here:
2025 Roadwork Projects: 2025 projects are still being determined. As projects are approved, they will be posted below:
-
Windsor Road - Charlie Grimm to CTH CV (Reconstruction) – begins July 28th
-
Depot Street - Windsor Road to 2nd Street, install angle parking on east side
-
CTH CV - water main replacement, sewer main replacement, guard rails, retaining walls, stormwater (2025) and road work, STH 19 to Vinburn Rd (2026)
-
Pulverize & Overlay
-
Brandywood Court
-
Brandywood Trail
-
Cranberry Court
-
Heatherstone Court
-
Heatherstone Ridge
-
Hamre Road
-
Lake Circle
-
Manthe Road - Work begins 7/21 - expect road closure during that week.
-
North Meixner Road - Started 7/15 with pulverizing and then the road widening will follow.
-
Winding Way
-
Winding Way Court
-
Morrison St. and Maple St. – final lift of asphalt & landscaping touch up.
- Crack Sealing & Chip Seal Project - Starting May 6, 2025
- Bear Tree Farms (Phase l)
- Windsor Gardens (Phase l)
- Forest Park Drive (STH 19 just north of Long Fellow Court)
- Revere Pass (Forest Park Drive to Forest Park Drive)
- Son of Liberty Drive (Forest Park Drive to West Dead End)
- Great Bridge Drive (Forest Park Drive to the West)
- Longfellow Court (Forest Park Drive to Cul-De-Sac)
- Traffic Signal at Windsor Road and CTH CV/Lake Road Intersection
- Approved by the Village Board by Resolution 2024-98. Project is anticipated to start end of March-August. It will occur in phases with underground work occurring first in Spring, roadwork in Summer and aboveground work occurring in the Fall.
Project Contact:
Davis Clark
Director of Public Works
608-888-0066
Updated 12/10/2024
